Friday, October 31, 2008

Halloween


A slight departure from the usual this year with the pumpkin carving:

Tuesday, October 28, 2008

Basement walls


The basement walls are mostly up - now working on the ceiling which requires a big beam - and is therefore taking some time!

Thursday, October 16, 2008

Slab, block and plumbing


They poured the slab, started on the block walls, and put in the basement plumbing.

Saturday, October 4, 2008

Street sign


We have a street sign - our new address will be 83 Beaver Pond Court.

Update: Here's a map.

Foundation


The foundation for the block walls has been poured.